UEFA about Gdańsk: Progress clearly visible
Gdańsk stadium on Letnica, PGE Gdańsk Arena has been visited by 17 person delegation, consisting of representatives of UEFA, Euro Poland Venture 2012 and PL.2012. The guests with a big interest have admired the constructed object.
more
more
Pomeranian Organizational Committee, about Euro 2012 in Gdańsk
The Fireplace Room of Provincial Office has become a place of the next meeting of Pomeranian Organizational Committee Euro 2012. The hosts of the meetings were: president of Gdańsk - Paweł Adamowicz and Pomeranian Vice Governor - Michał Owczarczak.
more
more
The airport: the agreement for the new terminal
The works concerning construction of the new passenger terminal on Lech Walesa Gdańsk airport will be commenced soon. The contract was signed on Wednesday, by virtue of which the consortium of Budimex and Doraco companies will construct terminal within 24 months, which is three months before UEFA Euro 2012™ launch.
more
more
10.12.2009 // PGE ARENA GDANSK
The Mayor of Gdansk Pawel Adamowicz announced the result of the contest for the naming rights sponsor of the stadium in Gdanskread more »
08.10.2009 // ”Together for the stadium”
”Together for the stadium”Social Committee of Euro 2012 Support, Społeczny Komitet Wsparcia Euro 2012, uniting representatives of dynamically acting companies in Pomerania, has inaugurated the action "Together for the new stadium". Its goal is to collect voluntary funds, which will serve as a support during equipping the stadium and in purchasing the equipment for young footballers. The first one thousand zloty was donated by the president of Gdańsk, Paweł Adamowicz.
read more »
29.05.2009 // The consortium of Hydrobudowa and Alpine started on time!
On the 28th of May the consortium of Hydrobudowa and Alpine began working on the platform in the VIP section of the stadium. This will allow to begin drainage works on Monday – the 1st of June. Finishing the first phase will lead to laying of the concrete foundations starting from the 15th of June.read more »
13.05.2009 // Gdansk will host the UEFA EURO 2012™!
The president of UEFA Michel Platini officially announced that the hosts of the UEFA EURO 2012™ in Poland are: Gdansk, Poznan, Warsaw and Wroclaw. This means that we finally have the long awaited confirmation of the fact that Gdansk will be one of the host cities of this spectacular event.read more »
09.05.2009 // Starting from the 4th of May 2009 Hydrobudowa Polska S.A. has began setting it’s building infrastructure at the construction site of the new stadium.
On the 8th of May 2009 Hydrobudowa Polska S.A. - Alpine is supposed to deliver the construction schedule and all the documents necessary to start their work at the site. After all the formal issues will be settled BIEG2012 will officially pass the construction site over into the hands of Hydrobudowa Polska S.A. - Alpine so from the 11th of May they will become the actual host of the construction site of the new football stadium in Gdansk.read more » more news »
| 28.03.2008 | RKW chosen as the stadium designer |
| 26.09.2008 | Building permit awarded |
| 30.09.2008 | Earthworks detailed design |
| 02.12.2008 | Earthworks and drainage system contract awarded to WAKOZ Sp. z o.o. |
| 15.12.2008 - 15.06.2009 | Earthworks and drainage system stage |
| 27.01.2009 | Submission of the design documentation, the specification of essential conditions of the order nad the invitation for offer submission to the seven potential contractors |
| 10.04.2009 | Selection of the main contractor - consortium of Hydrobudowa and Alpine Bau companies |
| 15.07.2009 | Placing of the foundation stone |
| 2nd qtr of 2009 - 4th qtr of 2009 |
Foundation works |
| 3rd qtr of 2009 - 4th qtr of 2010 |
Road works and external infrastructure |
| 3rd qtr of 2009 - 2nd qtr of 2010 |
Reinforced-concrete works |
| 1st qtr of 2010 - 3rd qtr of 2010 |
Steel structure works |
| 2nd qtr of 2010 | Perch |
| 2nd qtr of 2010 - 4th qtr of 2010 |
Finishing and interior fit up works |
| 20.01.2011 | End of construction process |
| 1st qtr of 2011 | Commissioning procedures |
| 2nd qtr of 2011 | First match |

|
PGE Arena Gdansk Country: Poland City: Gdansk Sports Club: KS Lechia Gdansk Capacity: 44 000 spectacles Dimensions: 236 x 203 x 45 metres Area of the plot: 33,9 ha Usable area: 36 600 m2 Design: RKW Rhode Kellermann Wawrowsky Construction Time: 2008 - 2010 Cost: 645 million PLN UEFA EURO 2012TM: within the framework of the games 3 group matches and 1 match of the quarter-finals shall take place at this stadium Visualisations of the stadium |
|